Computer Science ›› 2008, Vol. 35 ›› Issue (2): 301-302.

Previous Articles    

LI Xun, LI Peng ,GU Qing ,CHEN Dao-Xu (State Key Laboratory for Novel Software Technology, Nanjing University, Nanjing 210093)   

  • Online:2018-11-16 Published:2018-11-16

Abstract: Human cost takes great part in software project, but current Pert technology can not deal with human planning that is important in software project, unreasonable activity assignment may cause human idle or project postponement. This paper prompts a soluti

Key words: PERT, Critical path, Time estimate, Human planning